LAHORE – With the joint efforts of China and Pakistan, the integrated test and commissioning for the Orange Line Metro Train project, constructed by CR-NORINCO, passed the witness test by project owner’s representatives (NESPAK &CEC) on Friday.
This marked the satisfactory completion of the related scope of work as per the EPC contract which included electrical and mechanical (E&M) installations, system commissioning, test & commissioning, and test run.
The confirmation of installation quality, as well as system and linkage functioning by the project owner, laid a solid foundation for O&M handover of the project, which is of utmost importance for the project to smoothly proceed towards its public launch.